The proposal
The proposal for the construction of a temple and accommodation by Nan Hai Pu Tuo Temple of Australia Inc at Sellicks Hill.
Download a summary of this development (PDF, 203.7 KB)
The proposal comprises:
- shrines
- a pagoda
- ancillary accommodation for religious order
- retirement accommodation
- a feature statue
- memorial gardens
- Chinese gardens and associated parking.
The development is being undertaken in four stages.
- Stages 1 and 4 have been completed.
- Stage 2 is partially complete, with the main shrine nearing completion.
- Stage 3 remains to be commenced.
Assessment stages and documentation
Stage | Date | Documentation |
|---|---|---|
| Variation – ceremonial archway and memorial garden | 1 May 2026 | Decision Notice (PDF, 122.1 KB) |
| Extension of time – change to completion and/or commencement timeframes for Stages 2 to 3 | 23 February 2026 | Letter to applicant - extension of time (PDF, 89.8 KB) |
| Extension of time - change to completion timeframe for Stage 2 | 23 March 2023 | Letter to applicant - extension of time (PDF, 55.4 KB) |
| Extension of time - change to completion timeframes for Stages 2 and 3 | 16 February 2022 | Letter to applicant - extension of time (PDF, 326.7 KB) |
Variation - undercroft storage | 15 December 2019 | |
| Variation - storage shed | 11 April 2019 | Government Gazette dated 18 April 2019 |
Delegate of Governor's decision | 20 February 2014 | |
Decision by Governor | 21 February 2013 | |
Assessment report by Minister | 21 February 2013 | |
Response by proponent to public and agency comment on assessment document | 21 February 2013 | |
Release of assessment document by proponent for public comment | 22 September 2010 | |
Release of guidelines by Development Assessment Commission with level of assessment determined | 6 July 2009 | |
Declaration as major development | 18 December 2008 |