2 January 2025 - Release 3.101.08

DAP

Feature

Construction Industry Training Fund (CITF) threshold change

Effective 1 January 2025 development approvals issues after this date, the CITF levy payable by the project owner is now calculated on the estimated project value of building or construction works greater than $100,000.

Development applications with a building consent under assessment on or after 1 January 2025 the new threshold (works greater than $100,000) applies. To ensure that applicants have easy access to necessary information and maintain compliance with CITF levy requirements, the following enhancements have been made.

  • During application submission the question “Has the CITF Levy been paid? “ shows for development elements that require building consent approval and the total development cost exceeds $100,000.
  • When the CITF Levy is not paid submitters are advised “The CITF receipt number is required by PlanSA for Building Consent Approval” including a link to Lodge or Pay a Levy | Levies | Construction Industry Training Board.
  • More CITF Levy information is now available via a link to the Leviable Work Reference Table | Construction Industry Training Board.
  • Development applications with a building consent under assessment on or after 1 January 2025 and the total development cost is under $100,000 the CITF levy question is now hidden.

Visit About Levies | Construction Industry Training Board for more information.

Latest version